Results for the Second Quarter and Half Year
Udaipur. Hindustan Zinc Limited today announced its results for the second quarter and half year ended September 30, 2017. Chairman Mr. Agnivesh Agarwal said that Against a 5 year CAGR of 39% of our mined metal production, we expect this year’s underground growth to be over 60%, demonstrating one of the best transitions globally.
As our journey of 1.2 million MT of mined metal is coming closer, we are evaluating the next phase of our capacity expansion. The accelerating LME and record silver volumes are key drivers of our performance this quarter, though the higher commodity cycle is putting some pressure on our cost.”
Operational Performance : Mined metal production was at 219kt, 14% higher y-o-y, on account of higher volumes from underground mines. Q-o-Q production declined by 6% due to lower ore treatment. For H1, mined metal production was at 452kt, up 42% y-o-y driven by higher ore production across all mines.
Integrated zinc metal production was 192kt, 29% higher y-o-y and flat sequentially. Integrated lead metal production was 38kt, 24% higher y-o-y and 9% higher q-o-q. This was in line with availability of mined metal. Integrated silver production was at a record high of 140 MT, up 31% y-o-y and 22% q-o-q in line with higher feed from mines.
For H1, integrated zinc, lead and silver production were higher by 54% y-o-y, 32% y-o-y and 30% y-o-y respectively, in line with availability of mined metal.
Financial Performance
Revenues during the quarter were at Rs. 5,232 Crore, an increase of 37% y-o-y and 5% q-o-q (excluding excise duty of previous quarters, revenues would have been up 51% y-o-y and 16% q-o-q). The increase was on account of higher volumes and strong zinc & lead LME, partly offset by rupee appreciation. For H1, revenues were up by 55% y-o-y driven by the reasons mentioned above.
The zinc metal cost of production per MT before royalty (COP) during the quarter was at Rs. 63,288 ($984), up 17% y-o-y (22% in dollar terms) and flat compared to previous quarter. The y-o-y increase was primarily on account of 74% increase in dollar price of imported coal, almost doubling of metcoke prices and higher mine development, partially offset by increase in volumes. For H1, COP was higher by 10% y-o-y (15% in dollar terms) primarily on account of increase in coal and input commodity prices.
The above revenue and cost of production resulted in EBITDA at Rs. 3,052 Crore, up 47% y-o-y and 27% q-o-q while in H1 EBITDA increased by 70% y-o-y to Rs. 5,456 Crore.
During the quarter, exceptional gain was recorded related to reversal of royalty due to write back of Rs. 291 Crore of excess District Mineral Foundation liability for the period January 12, 2015 to September 16, 2015. This was pursuant to judicial pronouncement during the quarter.
Net profit during the quarter was at Rs. 2,545 Crore, up 34% y-o-y and 36% q-o-q while for H1 net profit was up by 50% y-o-y to Rs. 4,421 Crore. The substantial y-o-y increase in EBITDA was partly offset by higher tax rate and lower investment income on account of smaller corpus, in line with the guidance.
During the quarter, the Company sold 220kt of zinc and 30kt of lead forward at a price of $3,084 and $2,418 respectively. Of this, 165kt is for the period January to March 2018 and remaining is for April to June 2018.
Outlook : Production guidance is reiterated with mined metal to be higher than FY 2017, refined zinc-lead metal to be around 950kt and refined silver metal over 500 MT. Based on the significant increase in the commodity prices compared to last year, COP for FY 2018 is likely to be in the range of $900 – $950 per MT. The project capex for the year will be around $300-$325 million. The Company is on track to achieve 1.2 million MT per annum (mtpa) mined metal production capacity by FY 2020.
Expansion Projects : Capital mine development increased by 77% y-o-y and 11% q-o-q to 9,765 meters during the quarter across all mines. For H1, capital mine development was 18,593 meters, up 79% as compared to corresponding prior period.
Rampura Agucha : Mine development of 3,755 meter was achieved during the quarter. The main shaft service winder was commissioned during the quarter while the production winder installation has been completed in October 2017. Four ventilation fans of 2 MW each will be commissioned by year end. Shaft commissioning is on track and production is expected to start as per schedule in Q3 FY 2019.
Sindesar Khurd : Sindesar Khurd mine achieved mine development of 4,619 meters during the quarter. Main shaft equipping was commenced and production is expected to start in Q3 FY 2019. Construction, engineering works and procurement ordering is in full pace for the third mill of 1.5 mtpa capacity scheduled for commissioning by Q2 FY 2019. This will take the total milling capacity at Sindesar Khurd to 5.8 mtpa
Zawar : Zawar mine achieved ever highest mine development during the quarter 7,395 meter. During the quarter, the new Mochia decline was connected to production level enhancing its hauling capacity. Zawar mill debottlenecking was completed and the upgraded capacity of 2.7 mtpa was commissioned. Award of order for a second mill of 2 mtpa capacity was done during the quarter with commissioning scheduled by Q3 FY2019.
Fumer : The Fumer project at Chanderiya is progressing well as per schedule for completion by mid FY 2019. Structure erection and delivery of equipment material has commenced.
Interim Dividend : The Board of Directors has declared an interim dividend of 100% i.e. Rs. 2 per share on equity share of Rs. 2 each. Record date fixed for the interim dividend is October 31, 2017.
Liquidity and investment
As on September 30, 2017, the Company’s cash and cash equivalents was Rs. 19,979 Crore invested in high quality debt instruments. The Company also had Rs. 593 Crore of residual short term commercial paper out of Rs. 7,908 Crore raised in March 2017 to meet the special interim dividend fund requirement.
Earnings Call on Monday, October 23, 2017 at 3:30 pm (IST) – Dial In: +91 22 3960 0762
About Hindustan Zinc
Hindustan Zinc (NSE & BSE: HINDZINC) is the one of the largest integrated producers of zinc-lead with a capacity of 1.0 million MT per annum and a leading producer of silver. The Company is headquartered in Udaipur, Rajasthan in India and has zinc-lead mines at Rampura Agucha, Sindesar Khurd, Rajpura Dariba, Zawar and Kayad; primary smelter operations at Chanderiya, Dariba and Debari, all in the state of Rajasthan; and finished product facilities in the state of Uttarakhand.
Hindustan Zinc has a world-class resource base with total reserve & resource of 404.4 million MT and average zinc-lead reserve grade of 11.0%. The Company has a track record of consistently growing its reserve & resource base since 2003 and currently has a mine life of over 25 years.
The Company is self-sufficient in power with an installed base of 474 MW coal-based captive power plants. Additionally, it has green power capacity of 309 MW including 274 MW of wind power and 35 MW of waste heat power. The Company has an operating workforce of nearly 19,000 including contract workforce.
Hindustan Zinc is a subsidiary of the BSE and NSE listed Vedanta Limited (formerly known as Sesa Sterlite Limited; ADRs listed on the NYSE), a part of London listed Vedanta Resources plc, a global diversified natural resources company.